DHL Plainfield Mass Grading
Infrastructure work for a future 1.2mm SF Speculative Warehouse at corner of Ridge Road and 143rd Street.
- Over 1 Million Cubic Yards of Clay cut, excavated and filled
- Two (2) Detention ponds with associated utilities to drain the site
- 30 feet of structural fill material placed, and compacted
- Underground utilities to intercept and redirect adjacent farm field drainage tile
- Abatement and demolition of existing farm building and out-buildings
- Removal of underground wells and septic structures
143rd Street Plainfield, IL